Early LRT out of action? Free shuttle buses cover Universiti, Kerinchi and Abdullah Hukum 6.30am–9.30am

Malay Mail

KUALA LUMPUR, Nov 28 — Commuters at three Kelana Jaya LRT line stations will wait until 9.30am for their first train tomorrow, instead of the usual 6am start.

Rapid KL, the Klang Valley public transport operator, said Kerinchi, Abdullah Hukum and Universiti stations will open late for track replacement work.

Free shuttle buses will fill the gap from 6.30am to 9.30am, running every five to 10 minutes between Taman Jaya, Universiti, Kerinchi, Abdullah Hukum and Bangsar stations.

Tomorrow is the last of three Sundays set aside for the second phase of a seven-phase programme that began on September 13 and will run until September 2027.

Rapid KL said the work is aimed at keeping the tracks safe and reliable.

Stations not affected by the work will operate as usual.

The third phase will cover Dato’ Keramat, Jelatek and Setiawangsa stations on January 10, 17 and 24, 2027.

Universiti, Kerinchi and Abdullah Hukum stations will be hit again in the fourth phase on March 14, 21 and 28, 2027.

The fifth phase will cover Masjid Jamek, Dang Wangi, Kampung Baru, KLCC and Ampang Park stations on May 9, 16 and 23, 2027.

Date: 28 November, 2026 12:00 pm
Source: Malay Mail

💬 Join the Conversation! 💬

We’ve disabled comments on our posts and pages to keep the discussions organized and lively! But don’t worry – the conversation isn’t over. Head over to our forum and share your thoughts, ideas, and feedback with the community! It’s the perfect place to connect, learn, and engage with others who care about the same things. We can’t wait to hear from you!

Click here to join the discussion now! 🚀

💡 Want your business featured here?
Click here to advertise with us →
Scroll to Top