KUALA LUMPUR, Nov 17 — The government could face legal action and damage claims if it arbitrarily terminates contracts awarded to contractors for the Sabah Pan Borneo Highway (LPB) project without following established procedures and legal requirements.
Works Minister Datuk Seri Alexander Nanta Linggi said contract termination was not a decision that could be taken lightly, as contractors had legal rights, including the right to apply for an Extension of Time (EOT) if project delays were caused by factors beyond their control.
These include delays in site handovers arising from the government’s failure to finalise compensation payments for land acquisition.
“If the (state) Department of Lands and Surveys has not settled land acquisition compensation, contractors cannot access the site because landowners will not allow them to do so. In such cases, they are indeed entitled to claim an extension of time.
“We cannot simply terminate contracts at will. If we fail to comply with proper governance or legal requirements, they could take us to court and claim damages, which the government would then have to pay,” he said.
He was speaking as a guest on Bernama TV’s Ruang Bicara programme, titled “Empowering National Infrastructure Towards Sustainable Development”, last night.
Elaborating on land acquisition for the highway project, Nanta acknowledged that the process had also been delayed by political interference at the local level.
“We must admit that when directives (for land acquisition) are issued, political interference sometimes occurs. Local political leaders may intervene by making appeals, resulting in delays and prolonged waiting periods.
“This does not even take into account the costs and complexities involved in relocating utility infrastructure, such as cables and water pipes,” he said.
On the Sabah Pan Borneo Highway Phase 1 project, which the 2020 Auditor-General’s Report (LKAN) highlighted for its slow progress, Nanta explained that the figure reflected the combined performance of all 35 work packages under Phases 1A and 1B.
He said Phase 1B, comprising 19 work packages, only commenced in September 2024 but had already achieved 26 per cent physical progress and 23 per cent financial progress.
“As for Phase 1A, comprising 15 packages, which began much earlier, I acknowledge that there were serious shortcomings. However, physical progress has now reached 90 per cent, with four packages fully completed.
“The packages experiencing significant delays are Packages 1 and 2, located near the Sarawak border.
“If all 35 packages are combined into a single dataset, the overall progress percentage is inevitably pulled down by the problematic packages under Phase 1A,” he said.
Nanta said the Works Ministry (KKR) had accepted the findings and observations in the Auditor-General’s Report without taking a defensive stance. The ministry had also reorganised the deployment of Public Works Department (JKR) Sabah personnel to improve project administration and implementation on the ground.
He said the ministry was targeting completion of the entire Pan Borneo Highway project by 2030, guided by four key measures: a Completion Recovery Plan, ensuring land readiness, implementing cost controls for Phase 1B, and using an Audit Compliance Tracker to ensure all 13 findings in the Auditor-General’s Report were addressed within the stipulated timeframes.
The ministry had also established a Steering Committee, co-chaired by the State Secretary, to expedite coordination among agencies responsible for land acquisition and utility matters in Sabah.
In another development, Nanta said the Sarawak-Sabah Link Road (SSLR) project would feature the construction of Borneo’s first tunnel, which is expected to be more than two kilometres long.
He said the route would connect northern Sarawak to Sabah via Lawas, bypassing Brunei and eliminating the need for travellers to pay transit fees or undergo passport and immigration checks.
He added that the SSLR was being built to R3-standard rural road specifications, which are lower than the R5 standard used for the Pan Borneo Highway, but would nevertheless play an important role in improving connectivity to the interior areas of both states. — Bernama
Date: 17 November, 2026 10:00 am
Source: Malay Mail
💬 Join the Conversation! 💬
We’ve disabled comments on our posts and pages to keep the discussions organized and lively! But don’t worry – the conversation isn’t over. Head over to our forum and share your thoughts, ideas, and feedback with the community! It’s the perfect place to connect, learn, and engage with others who care about the same things. We can’t wait to hear from you!